Four lifts work in the theater at once, while the decorative painters begin the process of painting the ceiling of the theater to look like wood beams.
Monday, April 21, 2008
Sunday, April 20, 2008
Painting the Atrium
The decorative painting crew prepares to paint the atrium by protecting the 1926 wood columns.
Lead decorative artist Martha Tippin of Dean Tippin Studios works on pickling and staining the wood columns around the atrium.
One of the decorative painting crew works on blending small cracks in the columns which have been sealed and filled.
Saturday, April 19, 2008
Rigging
As soon as the stage could support weight, steel crews began reinforcing the structure at the top of the flytower which supports all the scenery and lightign equipment hoisted above the stage.

Following the steel crew, a team began installing the rigging system, for raising and lowering the lights and scenery. Dozens and dozens of cables were run from the overhead steel down to the stage, ready to be tied to long batons on to which the equipment is mounted. (a few can be seen at the left of the above photo with yellow caps on the ends).
Workers in lifts install lights in the scenery bay while new rigging on the stage is tested in the background.

Following the steel crew, a team began installing the rigging system, for raising and lowering the lights and scenery. Dozens and dozens of cables were run from the overhead steel down to the stage, ready to be tied to long batons on to which the equipment is mounted. (a few can be seen at the left of the above photo with yellow caps on the ends).
Workers in lifts install lights in the scenery bay while new rigging on the stage is tested in the background.
Friday, April 18, 2008
Theater Progress, November to February
Scaffolding goes up on the ground floor to allow the construction crew to plaster the underside of the balcony. The stage, poured at the top of November, will be ready for the Opening of Rigoletto in just 120 days.
Lifts work on stage while plastering continues both under and above the balcony.
Lifts work on stage while plastering continues both under and above the balcony.
drywall, plastering, and base painting are complete.
The theater takes on a warmer tone after many hours of work by the decorative painting crew.
Thursday, April 17, 2008
Finishing the Facade
New railings are installed on the facade balcony, matching the historic profile.
Workers from Aladdin Ward Electric install new lanterns on the facade.
A new lantern and a restored Opera House sign flank the imp sculpture on the corner of the Opera House.
Wednesday, April 16, 2008
Roof - Video
Tile work is almost complete on the main roof of the Opera House, while workers move tiles for installation on the portico in front of the Donna Wolf Steigerwaldt Courtyard.
Labels:
courtyard,
Donna Wolf Steigerwaldt,
Opera House,
Renovation,
Roof
Tuesday, April 15, 2008
Lifting to the Roof - Video
A large crane spends the day in front of the Opera House lifting the final pieces of air conditioning duct work to the roof for installation.
Subscribe to:
Posts (Atom)







































