Thursday, January 3, 2008

Orchestra Pit Construction, Part 5




The walls and floor of the pit are finished and preparation begins for forming the stage.

See Part 1, Part 2, and Part 3, Part 4

Also, see the photos of the excavation before the pit construction began:
Part 1
Part 2

Wednesday, January 2, 2008

Railings - Video





Carpenters from Adams Brothers Cabinetry build and install a new section of railing at the third floor of the atrium.

Monday, December 31, 2007

Lifts





Painters and plasterers begin work on the ceiling and walls of the theater using lifts.

Friday, December 28, 2007

Margaret Shaw-Romanes



Director of Development Melissa Burtless takes a tour of the theater with longtime volunteer Margaret Shaw-Romanes and Individual Giving Officer Courtney Balok

Thursday, December 27, 2007

Roof Truss

To allow the removal of a pair of columns left in the balcony by the removal of our projection booth, a truss was designed to carry the roof load to the outside walls of the theater. The photos below show its installation.


Portions of the roof truss over the rear of the balcony are put in place by crane.

The truss is covered over in a layer of insulation.



The truss is covered in a layer of sheet metal and awaits its final layer of roofing.

Wednesday, December 26, 2007

Digging Out the Pit - Video




The last of the pit is cleared out so the forming of the walls and floor can be completed.

Friday, December 21, 2007

Skylight






A few views of the skylight on sunny days during construction this summer and fall.