Thursday, February 28, 2008
Wednesday, February 27, 2008
Decorative Painting
Tuesday, February 26, 2008
Hammering
Monday, February 25, 2008
Friday, February 22, 2008
Thursday, February 21, 2008
Wednesday, February 20, 2008
Tuesday, February 19, 2008
Pit and Stage
Monday, February 18, 2008
Exterior Painting
One of the painting crew carefully re-attaches the 'Donna Wolf Steigerwaldt Courtyard' lettering.
Friday, February 15, 2008
Welding - Video
Welders work on the stage and the balcony to prepare the new control booth on stage, and the lighting rail on the front of the balcony.
Thursday, February 14, 2008
Finishing Touches
One of the construction crew works on staining trim for the third floor Founder's Lounge dinning room.
Wednesday, February 13, 2008
Tuesday, February 12, 2008
Friday, February 8, 2008
Thursday, February 7, 2008
Steel Work Above the Stage - Video
Large scaffolding is setup and moved around stage to work on reinforcing the steel structure above the stage. Rigging equipment which is used to life lights and scenery will be mounted off of the steel structure.
Wednesday, February 6, 2008
Monday, February 4, 2008
Friday, February 1, 2008